Current Building Structure
Hughes:
16 classrooms total
13 General Ed Classrooms
(Resource Room, Music or
Art would have to be displaced in order to have enough classrooms to house 14
classes)
(7/grade level x 2 grade
levels=14)
Would also need to add a CI
classroom
Currently:
1-Rk
2-K
2-1st
2-2nd
2-3rd
2-4th
2-5th
1-Resource Room
1-Art Room
1-Music Room/Nurses Office
Gordon:
13 classrooms total
12 General Ed Classrooms
(1 currently housed in the purposed music room)
Music and Art as well as the technology computer lab would have
to be displaced in order to have enough classrooms to house 14 classes
(7/grade x 2 grade
levels=14)
Would also need to add a CI
classroom
Currently:
2-k
2-1st
2-2nd
2-3rd
2-4th
2-5th
1-Music/Art Room (Music was
already displaced from it's bond money space due to 5th grade)
1-Resource Room (Housed at the Shamrock Preschool side due to
displacement from 5th grade)
Walters:
21 classrooms total
18 General Ed Classrooms,
CI classroom is smaller than a purposed classroom, 4 Classrooms would sit empty
Currently:
3-K (1 in the purposed resource room
due to 5th grade)
3-1st
2-2nd
3-3rd
3-4th
3-5th
1-CI
1-Resource Room
1-Music Room
1-Art Room (resource
room shares this space when art is not there due to 5th grade)
This clearly indicates that 2 of our schools cannot possibly
house the number of students we currently have enrolled, while the third
wouldn't be utilizing all of the space that it was intended to use.